Project Updates
Sign up for State Road 37 Improvement updates here

As the SR 37 Improvement Project moves forward, the City of Fishers will provide project updates on this page. While updates will become more frequent as the project progresses, this page will only be updated as needed during the environmental study and design phase of the project.  

May 2017
Starting May 1, geotechnical drilling will begin along the State Road 37 corridor as part of the final design phase of State Road 37 Improvement Project. Lane and shoulder restrictions will be active through the June 30.

Motorists will see staked locations along the corridor starting with the 141st Street intersection. The geotechnical drilling will cause lane restrictions from 131st Street through 146th Street through June 30. Southbound restrictions will not begin until 9am daily and northbound restrictions will be done daily before 4pm to allow for maximum traffic flow during peak hours.

State Road 37 turn lanes will not be affected during lane closures and crews will maintain a minimum of one throughlane at all times. 

April 2017

On April 18, 2017, an information meeting will be held for homeowners in the project area along SR 37 at Delaware Township Event Center. The meeting presentation and minutes will be posted within 10 days of the meeting. 

January 2017

On January 30, 2017, an information meeting was held at Delaware Township Community Center for homeowners and businesses residing along the SR 37 corridor. A presentation and project update was provided, followed by Q&A. Attendees were given the opportunity to visit with team members at tables to look at Stage 1 Designs, ask questions and give feedback. 

Presentation
Minutes


December 2016

On December 14, 2016, a Community Advisory Committee meeting was held regarding the SR 37 Improvement project from I-69 to 146th Street.

Meeting Notice
Minutes


October 2016

On October 19, 2016, an information meeting was held for homeowners living along the corridor at the Delaware Township Community Building. Below are the links to the meeting presentation and minutes.

Meeting Presentation
Minutes


September 2016

General survey work has been completed. Crews will still be on site monitoring wells along the corridor over the next year. While lane closures will not be in place, vehicles will be parked along the shoulders.

On September 21, 2016, an information meeting was held at Ben & Ari's for local business owners. Below are the links to the meeting presentation and minutes.

Meeting Presentation
Minutes


July 2016

On July 27, 2016, an information meeting was held for homeowners in the project area along SR 37 at Fishers Junior High. Below are links to the meeting presentation and minutes. 

Meeting Presentation
Minutes


June 2016

On June 18, 2016, an information meeting was held for business owners in the project area along SR 37 at Pinheads. Below are links to the meeting agenda and minutes.

Meeting Agenda
Minutes


May 2016

Various geotechnical work will begin the week of May 16, 2016 along the corridor. Work will take place starting at the 126th Street intersection. Geotechnical work includes taking soil samples and testing for wet walls, necessary to determine how deep the ground water table is. Kick off meetings scheduled for May 16 and May 17, 2016.

May 2016

Initial contracts were awarded on May 9, 2016 and preliminary work is underway along the corridor.


Questions? Please contact .