| Signal Equipment Modernization 45% Complete |
| 96th & Hague/North by Northeast Friday 4/27 Monday 4/30 |
| Please check this site for updates or sign up for Fishers Alert or the Drive Fishers Twitter account. Traffic Patterns will change frequently! |
| Click here to view larger interactive map of project area |
| Town of Fishers Contact: Tami Otto Project Engineer Phone: (317) 595-3160 Fax: (317) 595-3164 Design Firm: A&F Engineering Contractor: James H. Drew Construction Start Date: March 2012 Construction Completion (est.): July 2012 Project Cost (est.) Construction: $ 250,000 |
| |