| 126th St. Construction Project Phase II 93% Complete |
| Update: 5-11-12 Paths, sidewalks and sod are going in now. Contractor is scheduled to be completed June 15, 2012. |
| Please check this site for updates or sign up for Fishers Alert or the Drive Fishers Twitter account. Traffic Patterns will change frequently! |
| Click here to view larger interactive map of project area |
| Town of Fishers Contact: Tami Otto Project Engineer Phone: (317) 595-3160 Fax: (317) 595-3164 Design Firm: R.W. Armstrong Contractor: Berns Construction, LLC Construction Start Date: June 2011 Construction Completion (est.): June 2012 Project Cost (est.) Design: $ Construction: $ 10,271,393 |
| |