Past Construction Projects

Past Projects

  • I-69 New interchange with 106th Street - $24,000,000 federal funds
  • 96th Street and Lantern Road roundabout - $2,400,000 federal funds
  • 106th Street and Cumberland Road roundabout - $1,792,000 federal funds
  • Cyntheanne Road rehabilitation - $900,000 federal funds
  • 2017 - Extension of Nickel Plate Trail from Municipal Complex to Conner Prairie - $1,228,800 federal funds
  • 2017 - 113th Street road rehabilitation from Olio to Florida - $1,825,600 federal funds
  • 2018 - 113th Street and Florida Road intersection improvement - $2,013,185 federal funds
  • 2018 - 126th Street and Allisonville Road intersection improvement - $2,730,186 federal funds
  • 2018 - 131st Street and Cumberland Road intersection improvement - $1,445,417 federal funds
  • 2017 - 116th Street pedestrian upgrades (crosswalks, HAWK, signals) - $792,450 federal funds
  • 2018 - 131st Street and Allisonville Road intersection improvement - $3,518,400 federal funds
  • 2018 – Installation of School Zone Flashers - $450,000

Tentative Future Projects* 

2019

  • 2019 - 96th Street between Lantern Road and Cumberland Road, addition of travel lanes - $7,535,224 federal funds
  • 2019 - 136th Street and Cyntheanne Road intersection improvement - $2,136,000 federal funds
  • Cumberland Road between 106th Street and 116th Street road rehabilitation - $4,536,000 federal funds
  • 2019 - 126th Street and Reynolds Drive intersection improvement - $1,918,183 federal funds

2020

  • 2020 – Geist Greenway Phases 1 and 2 - $2,500,000
  • 2021 – Southeastern Parkway and Cyntheanne Road Roundabout - $2,261,250
  • 2022 – 106th Street and Hoosier Road Roundabout - $1,413,450

*Grant totals and timelines exceeding 2019 are all tentative and subject to change.